Saturday, February 22, 2014

Enercon Case: Pro-Arbitration Approach and Determination of Arbitration ‘Seat’


In what can termed as an important development in Arbitration Law, the Supreme Court of India (“Supreme Court”) has delivered a 129-page judgment wherein issues such as ‘factors determining seat of arbitration’, ‘concurrent jurisdiction of foreign court’ etc. have been discussed. In Enercon (India) Ltd. & Ors v. Enercon GMBH & Anr. , the Supreme Court had to decide appeal(s) against two judgments of Bombay High Court – one judgment which allowed the application of the respondent under section 45 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) and other  judgment vacating the anti-suit injunction issued against the respondent.

Before going to and discussing underlying issues, it would first be important to understand the factual background.

Factual Background: In 1994, Appellants no. 2 and 3 (“Members of Mehra Family”) entered into a Joint Venture Agreement (“JVA”) with Respondent no. 1 (“Enercon GMBH”) to incorporate Appellant no.1 [“Enercon (India) Ltd.”]. The objective behind incorporating Appellant no.1 was to manufacture and sell Wind Turbine Generators (“WTG”). In furtherance of JVA, both the parties executed certain agreements which included Share Holding Agreement and Technical Know How Agreement (“TKHA”) (these agreements were later amended). 

After the expiry of TKHA, there were further negotiations between the parties. These negotiations, which were recorded in a document titled ‘Heads of Agreement’, sought to explore the possibility of agreement to transfer future technology developed by the Respondents. Following these negotiations, parties entered into ‘Agreed Principles’, which were meant to be the basis of all the final agreements. On the same day when ‘Agreed Principles’ were executed, parties also executed and signed Intellectual Property License Agreement (“IPLA”). IPLA contained an arbitration clause (Clause 18) which can be read as follows:

17 GOVERNING LAW
17.1  This  Agreement  and  any  dispute  of  claims arising out of or in connection with its subject matter are  governed  by  and  construed  in  accordance  with the Law of India.

18. DISPUTES AND ARBITRATION

18.1 All disputes.....................any  Party  may refer  dispute(s), controversy(ies) or difference(s) for resolution  to  an  arbitral  tribunal  to  consist  of  three (3) arbitrators, of who one will be appointed by each of  the  Licensor  and  the  Licensee  and  the  arbitrator appointed by Licensor shall also act as the presiding arbitrator.

18.2 ....................

18.3  A  proceedings  in  such  arbitration  shall  be conducted  in  English.  The venue of the arbitration proceedings shall be in London. The arbitrators may (but  shall  not  be  obliged  to)  award  costs  and reasonable  expenses  (including  reasonable-fees  of counsel)  to  the  Party  (ies)  that  substantially  prevail on  merit.  The provisions of Indian Arbitration and Conciliation Act, 1996 shall apply........”

As disputes arose between the parties, Respondent(s) sought to initiate arbitration proceedings thereby nominating an arbitrator. Respondents further sought to file an ‘Arbitration Claim Form’ before the English High Court. This initiation of arbitration was resisted by the Appellants on the ground that there was no ‘concluded contract (IPLA)’ and hence there was no question of arbitration. While Appellants claimed that IPLA was not a concluded contract because of its non-conformity with ‘Agreed Principles’, Respondents claimed it to be a binding contract.

In furtherance of resisting arbitration, Appellants filed a Regular Suit (“Daman Suit”) before Daman Trail Court (“Trial Court”) for a declaration that there subsists no concluded contract and hence no question of arbitration. On this issue, Trail Court decreed in Appellant’s favour thereby ordering Respondents to maintain status quo. In the meantime, Appellants, without prejudice, nominated Justice B.P. Jeevan Reddy as their nominated arbitrator. However, Justice Reddy, along with the Respondents’ nominated arbitrator, was of the opinion that arbitration agreement is not workable. That is, expressed their inability to appoint a third arbitrator. (Read the above arbitration clause, wherein it first provided for THREE arbitrators and thereafter provided that arbitrator appointed by the Licensor would also be presiding arbitrator).

Following this development, two more applications were filed in the Daman Suit – one by the Respondents (under Section 45, Arbitration Act) and other by the Appellants (seeking anti-arbitration injunction for restraining Respondents to proceed before English High Court). The Trail Court allowed both the applications of the Appellants and rejected section 45 application of the Respondents.

Against the orders of the Trial Court in Daman Suit, Respondent filed appeals before the Daman Appellate Court (“Appellate Court”). The Appellate Court set aside the orders of the Trail Court. Against these orders of the Appellate Court, Appellants filed two writ petitions before the Bombay High Court. Initially, Bombay High Court restored Trial Court’s order in Daman Suit but later, while finally disposing off the petitions, it dismissed the writ petitions filed by the Appellants. High Court further held that London is not the seat of arbitration but English courts will have concurrent jurisdiction.

Initially when Bombay High Court had restored Trail’s Court order in Daman Suit, Respondents had filed arbitration application (for constituting arbitral tribunal) before English High Court. Consequent to this, English High Court ordered the Appellant to expedite proceedings before the Bombay High Court. When Bombay High Court finally disposed off the petitions, Respondents again approached English High Court for constituting arbitration tribunal and further asking anti-suit injunction against the Appellants (to restrain them from filing of Special Leave Petitions against the orders of Bombay High Court). The English High Court was, however, of the opinion that matter should first be considered by the (Indian) Supreme Court; otherwise, there may be a possibility of conflicting decisions. This is how the present matter reached the Supreme Court.

Issues:

Following can be considered as the major issues framed by the Supreme Court (¶ 69):

(i)            Concluded Contract: Whether IPLA, which was allegedly executed and signed by the parties, is a concluded contract? Whether this issue should be decided by the court or arbitral tribunal?

(ii)          Arbitration Agreement: Whether there exists a valid Arbitration Agreement? Whether it is unworkable?

(iii)           Seat of Arbitration: What is the seat of arbitration? This issue is important since courts of arbitration seat exercises supervisory jurisdiction over arbitration proceedings. (Clause 18.3 of Arbitration clause (see above) which referred London as the venue arbitration).

(iv)          Concurrent Jurisdiction: Whether courts in India and England have concurrent jurisdiction? Linked to this, whether, Appellants would be entitled for anti-suit injunction against the Respondents?

Validity of Arbitration Agreement Independent of the Underlying Contract

On the question whether there was a concluded contract, the Supreme Court was of the opinion that even if the existence of main contract is under dispute, it may not affect the validity of arbitration clause. Opining that there were no factors which indicated arbitration agreement to be null or void, the Court held that parties have  irrevocably  agreed  that clause  18  of  the  proposed  IPLA  shall  apply  to  settle any dispute or claim.

Since it was the intention of the parties to arbitrate, the question of concluded contract becomes irrelevant. That is, disputed as regards concluded contract will have no effect on the existence of arbitration agreement. In reaching this conclusion, concept of severability of arbitration agreement was also emphasised. The opinion of the Court also reflected a pro-arbitration approach:

“.......Whilst interpreting the arbitration agreement and/or the arbitration clause, the court must be conscious of the overarching policy of least intervention by  courts  or  judicial authorities  in  matters  covered  by  the  Indian Arbitration Act, 1996.......”

Regarding the question as to which forum should decide the existence of concluded contract, it was held that that the same can be decided by the arbitral tribunal. This is because the arbitration clause was widely worded and would include such disputes.

Interpretation and Workability of Arbitration Clause and ‘Bystander Principle’

To address this point, the Supreme Court again adopted a pro-arbitration approach. It was of the opinion that, unlike statutory provisions, an arbitration clause cannot be construed with the application of strict rules of interpretation. And, it would be the obligation of the court to make arbitration clause workable with the permissible limits of law:

“......following  the  UNCITRAL  Model  Law,  that  the Courts  play  a  supportive  role  in  encouraging  the arbitration to proceed rather than letting it come to a grinding  halt.” (¶ 84)

Opining that un-workability of arbitration clause is attributed only to the machinery provision, the missing line (“the  two  Arbitrators  appointed  by  the  parties  shall appoint  the  third  Arbitrator”) can be read into the arbitration clause. In doing so, the court applied bystander principle’ which, according to Lord Justice MacKinnonn, can be described in the following terms:

“prima facie that which in any contract is left to be  implied  and  need  not  be  expressed  is something  so  obvious  that  it  goes  without saying; so that, if, while the parties were making their  bargain,  an  officious  bystander  were  to suggest  some  express  provision  for  it  in  their agreement, they would testily suppress him with a common 'Oh, of course!” Shirlaw v. Southern Foundries, [1937 S. 1835]

Having concluded that there exist a manifest intention of the parties to arbitrate, the crucial line which seems to be an omission or an error can be inserted by the Court.  Reliance was placed on Shin Satellite Public Co. Ltd. Vs. Jain Studio Ltd, (2006) 2 SCC 628.

‘Seat of Arbitration’: India or London? What are the Factors which Court considered?

Having come to the conclusion that there exists a valid arbitration agreement which is workable, the Court dealt with the critical issue of arbitration ‘seat’. The court rejected the contention of the Respondent that the usage of term ‘venue’ would indicate that London is the seat of arbitration. Rather, it was held by the court that London only be treated as a geographical location for arbitration hearings and proceedings:

“.....where in substance  the  parties  agreed that the laws of one country will govern and control a given arbitration, the place where the arbitration is to be heard will not dictate what the governing law  will be.”(¶ 108; Case referred: Braes of Doune Wind Farm (Scotland) Limited Vs. Alfred McAlpine Business Services  Limited, [2008]EWHC 426 (TCC)]

According to the Court, the fact that all three laws, i.e., law governing the Contract, the law governing the arbitration agreement and law governing arbitration proceedings (curial law), were Indian is a strong indicator that seat of arbitration is India. Having chosen these three laws, the parties, in the opinion of the court, could not have intended to create a difficult situation by choosing London as the seat of arbitration. It is more so when parties have not chosen a supranational body of rules but Indian Arbitration Act for arbitration.

There was another important point. Seat of arbitration also carries with it the jurisdiction of challenge an arbitral award. If London is considered to be seat of arbitration, it would mean that challenge to award would also be in London or English Courts. But in the present case, parties had chosen Arbitration Act for arbitration, Part I of which will also be applicable. Hence, holding London as the seat of arbitration would lead to undesirable results (e..g., challenging award at both the places). (Court opined that in the present case, Bhatia judgment and not BALCO judgment will be applicable.)

In concluding that India is the seat of arbitration, Supreme Court also considered the closest connection test. According to this, the law with which the agreement to arbitrate has its closest and most real connection is the law of the seat of arbitration. In the present case, apart from the three laws for the purpose of arbitration, performance of agreement was also meant in India. (Referred case: SulameRica Sulamerica CIA Nacional de Seguros SA and others v Enesa Engenharia SA & Ors, [2012] EWCA Civ 638

The Court also rejected the application of case relied by the Respondents on the ground that they relate to phrases such as ‘arbitration in London’. This, in the opinion of the court, cannot be equated with the phrase ‘venue of arbitration proceedings shall be in London’. In conclusion, it was held by the court that merely because arbitration can be conducted in a venue (London) would not mean that seat of arbitration has also been changed. Such venue can be chosen for the purpose of convenience.

“.....the placement  of  the words  that  "the  Indian  Arbitration  and  Conciliation Act shall apply" in the last clause 18.3 indicates the specific intention of the parties to the application of the Indian Arbitration Act, not only to the Arbitration Agreement  but  also  that  the  curial  law  or  the  Lex Arbitri  would  be  the  Indian  Arbitration  Act.....”

Can Courts of Both the Countries (India and England) have Concurrent Jurisdiction?

Having come to the conclusion that India is the seat of arbitration, it was not difficult for the court to hold that only Indian courts would have supervisory jurisdiction over arbitration proceedings. Holding otherwise, in the opinion of the court, would create unnecessary inconvenience and problems.

As per the Court, an agreement providing seat of arbitration is analogous to exclusive jurisdiction clause. In the present case, though there was no specific mention of India as the seat of arbitration, it was nonetheless concluded that India is the arbitration seat. Hence, the conclusion to hold India as seat of arbitration would confer exclusive jurisdiction over Indian courts.

Consequently, the court held that English Courts would not have concurrent jurisdictions over the arbitration proceedings. The Respondent no.1 had chosen Indian Law for contract and has further participated in litigation before Indian Courts. Hence, in the opinion of the court, these factors indicate that Respondent no. 1 does not consider India to be forum-non-conveniens. On the basis of this, the court restored the anti-suit injunction (Daman Trail Court, see ‘Factual Background) issued against the Respondents.

 (Note: Reference to ‘Bhatia Judgment’ in this post should understood as the decision of the Supreme Court in Bhatia International v. Bulk Trading S.A. (2002) 4 SCC 105 . And, reference to ‘BALCO Judgment’ should be understood as the decision of the same court in “Bharat Aluminium Company Vs.  Kaiser Aluminium, (2012) 9 SCC 552)



No comments :

Post a Comment