On Wednesday, the High Court of Delhi (“Delhi
HC”), in the case of Organising
Committee Commonwealth Games, 2010 v. M/s Nussli (Switzerland) Ltd., has allowed a petition under section 9 of
the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) thereby granting
injunction against the Respondent [“M/s
Nussli (Switzerland) Ltd.)] in ‘post-award’
stage. In reaching its conclusion, Delhi HC had declined to consider a judgment
of the High Court of Bombay (“Bombay HC”), on a similar point, as a precedent.
Facts:
In 2010, the Respondent was awarded a turnkey contract for providing overlays
on rental basis for the Commonwealth Games, 2010 (“Games”). In order to secure
the contract’s performance, the Respondent was required to furnish a ‘performance bank guarantee’ (“PBG”)
equivalent to the 10 % of the contract value (which Respondent furnished). Following
the conclusion of the Games, disputes arose between the parties and the matter
was referred to arbitration (in 2012). From time to time, the Respondent was
restrained to encash PBG; first as a
result of petition (sec.9) filed by the Petitioner and then because of a direction issued by the
Arbitral Tribunal.
Partly allowing the claim of the
Respondent and further allowing Appellant’s claim to a small extent, Arbitral
Tribunal made an award in Respondent's favour (after adjusting amount). At
this juncture, the Petitioner made a counter-claim seeking refund of a certain
amount on the ground that contract was vitiated by fraud; this claim was rejected.
Following this, as Petitioner intended to
challenge the arbitral award, it filed the present petition under section 9 of the Arbitration Act for keeping PBG alive. Initially, Delhi HC passed an order thereby
ordering the Respondent to keep PBG alive and listed the matter for next hearing. Against this order, the
Respondent preferred an appeal before the division bench of the Delhi HC - this appeal was disposed off when the Respondent agreed to keep PBG alive for
certain period and the hearing of the present petition was re-opened.
Contentions:
On behalf of the Petitioner, it was contended
that since PGB would lapse before the Petitioner challenges award under section 34 of the Arbitration Act, PBG should be kept alive. It
was further contended that since the Respondent is a ‘foreign entity’ with no assets in India, the Petitioner would be left
remediless if its application under section 34 succeeds. Further, it was
contented that in a different proceeding, PGB has been attached by the Income Department;
hence, the Respondent was only interested in getting PBG released.
On behalf the Respondent, it was contended
that as contemplated under section 9 of the Arbitration Act, interim measures in
post-ward stage are for the
benefit of the
party who seeks enforcement of the
Award. To substantiate this, reliance was placed on the decision of Bombay
HC in Dirk India Pvt. Ltd.(DIPL) Vs. Maharashtra State Electricity Generation
Company Limited, MANU/MH/0268/2013
(Appeal No.114/2013). In Dirk (supra), it was held by the Bombay
HC that once an award is rendered by the arbitral tribunal, interim measures
under section 9 of the Arbitration Act cannot be sought by the party against
whom award has been made. Holding otherwise, in the opinion of the court, would
negate the sanctity and efficacy of arbitration process:
“.....the object and purpose of an interim measure after
the passing of the arbitral award but before it
is enforced is
to secure the
property, goods or amount
for the benefit of the party which
seeks enforcement....”
“.....to hold
that a petition
under Section 9 would
be maintainable after
the passing of
an arbitral award at the behest
of DIPL whose claim has been rejected
would result in
a perversion of
the object and
purpose underlying Section 9 of the Arbitration and Conciliation Act, 1996.....”
“.....What such
a litigating party
cannot possibly obtain
even upon completion of
the proceedings under
Section 34, it
cannot possibly secure in a petition under Section 9 after the award....”
(Note: Against
the above-mentioned judgment of the Bombay HC, an appeal is pending before the
Supreme Court)
Against this point, it was contended by the Petitioner that because of different facts
and circumstances, the Bombay HC’s judgment in Dirk (supra) would not be applicable to the present case.
On behalf of the Respondent, it was further
contend that, (i) as a result of award being passed against it, prima facie case has been established
against the Petitioner; (ii) the Respondent is incurring heavy losses in keeping PBG alive; (iii) attachment of PBG by the
Income Tax Department is illegal.
Findings of the Delhi HC:
The Delhi HC decided
in favour of the Petitioner. In the opinion of the court, the Bombay HC’s
decision in Dirk (supra) cannot be
relied since the same was rendered in entirely different factual context. In Drik (supra), the party was seeking
interim measure for continuing the
contract; however, in the present case, Petitioner had been challenging the
validity of the contract itself.
While granting interim measure in the present case, a reference was
also made to Order XXV Rule of Code of Civil Procedure, 1908 (“CPC”). According
to this provision, plaintiff, who is a 'foreign party', is required to furnish
security for costs. In the present
case, the Respondent was a foreign party; hence, petitioner’s right to challenge
arbitral award cannot be rendered otiose by
allowing the Respondent to encash
PBG.
Conclusion: The Respondent was required to keep PBG
alive till the disposal of the objection petition under Section 34 of the Act
that may be preferred by the petitioner within the period of limitation.
No comments :
Post a Comment